| 所組別: | 工業工程學系博士班 | 科目: | 工業工程基礎科目 --作業系統 | 考試時間: | 06月09日第 1節 |

| (a) | (5pts)Draw a graph of the constraints and shade in the feasible region. Label the vertices of the feasible region. |
| (b) | (2pts)Use (a) to find the optimal solution and the optimal value. |
| (c) | (3pts)Find the shadow prices in each constraint. |
| (d) | (5pts)Find the ranges associated with the two coefficients of the object function. |
| (e) | (5pts)Find the righthand-side ranges for the three constraints. |
| (f) | (5pts)Solve this problem by the simplex method. |
| (a) | (5pts)the probabiblity that the secretary is busy. |
| (b) | (5pts)the mean number of jobs waiting for her processing. |
| (c) | (5pts)the mean length of time that a job can be finished after it is given to the secretary. |
| (d) | (5pts)the probability that an arriving job will be completed in 40 min. |
| (e) | (5pts)If the secretary can have 50 dollars for each job she finishes, but there is also a penalty 10 dollars for each job of which delay exceeds 40 min. Assume this secretary works 8 hours a day. What is her mean income for each day. |